Sample Bill

Sample Bill of Quantities for Building Construction (Perth Example)

A bill of quantities (BoQ) breaks a building project into measured items so every contractor prices exactly the same scope. This page shows what a BoQ for building construction looks like: the main sections and typical measured items. It also explains how to read one and how to use it after the contract is signed.

If you want the step-by-step method, read how to create a bill of quantities.

What is in a bill of quantities?

A BoQ is usually prepared by a quantity surveyor from the drawings and specification. It has:

  • a preamble explaining the measurement method and pricing rules;
  • measured sections by trade or element, each item with a description, unit and quantity;
  • provisional sums and prime cost items for work not yet fully designed or selected;
  • a summary page collecting the section totals.

Typical sections in a building BoQ

Preliminaries

  • Site establishment, temporary fencing and amenities
  • Supervision and site management
  • Insurances, permits and fees
  • Scaffolding, cleaning and waste removal

Site preparation and earthworks

  • Clearing, stripping topsoil and levelling the building pad
  • Imported fill and compaction, which is common on Perth sand lots
  • Excavation for footings and service trenches
  • Retaining walls where the site slopes

Foundations and substructure

  • Strip and pad footings (concrete m³, reinforcement kg or m)
  • Concrete slab on ground, with mesh, membrane and edge beams
  • Termite management systems

Superstructure

  • External double-brick cavity walls or brick veneer (m²)
  • Internal brick or framed walls (m²)
  • Lintels, wall ties and damp-proof courses
  • Roof framing, roof cover, sarking, gutters and downpipes
  • Windows and external doors (number)

Internal finishes

  • Wall render or plaster, and plasterboard ceilings (m²)
  • Waterproofing to wet areas (m²)
  • Floor and wall tiling (m²)
  • Internal doors, joinery and painting

Services

  • Electrical points, switchboard and lighting
  • Plumbing, sanitary fixtures and hot water
  • Air conditioning
  • Smoke alarms

External works

  • Driveways, paths and paving
  • Fencing, letterbox and landscaping
  • Stormwater soakwells and drainage

How to read a BoQ

  • Description: what the work is, including material, size and standard.
  • Unit: how it is measured (m, m², m³, kg, no., item).
  • Quantity: the net measured amount, without waste unless the preamble says otherwise.
  • Rate: filled in by the tenderer, including labour, materials, plant, waste and usually overheads and margin.
  • Amount: quantity × rate.

How a BoQ is used after the contract is signed

  • Progress claims: the percentage complete of each item is valued at the contract rates.
  • Variations: added or omitted work is valued using the same rates.
  • Final account: provisional sums are adjusted to actual cost and variations are reconciled.

Benefits of using a BoQ

  • Like-for-like tender comparison.
  • Clear scope, so fewer disputes about what was included.
  • Agreed rates for variations and claims.
  • Better resource and procurement planning.

Related: what is a bill of quantities?, BoQ vs bill of materials and BoQs for structural steel works.

Frequently asked questions

Can I use this sample as a template?

You can use the structure. Quantities and rates must come from your own drawings and current quotes.

Who fills in the rates?

In a tender BoQ, the contractors do. A quantity surveyor may also price a copy as a pre-tender estimate.